Challenge

  • General approach needed for monitoring and control of processes.
  • 3 waves Green belt ( approx.40) and 10 Black Belts trained
  • Improvement projects in Logistics and Infrastructure planning, Financial Services, Data management of Energy consumption
  • Characteristics Six Sigma (client is leading, fact-based decisions, focus on results, short-cyclical) fit with existing policies (value creation, client focus, professionalization)
  • Transparant processes and control as springboard to Excellence and Innovation



Our solution

  • Advising steering committee, training and coaching
  • Training and on-the-project coaching of improvement teams
  • Training change management
  • Six Sigma business cases

Results


Example results projects:

  • Collections: cost reduction (€ 200.000), DSO reduction (3 days)
  • MDDS: measurement quality (99% within 10 days), FTE reduction (14)
  • Infra: materials on time, stock reduction (€ 775.000), eliminate scrap (€ 80.000 per year)
Contact
Atos Consulting
+31 (0)88 265 8518
e-mail: Email this contact

Key Facts

Industry

Utilities & Energy


Service Line

Atos Consulting


Solution Area

Financial Leadership
Risk & Process Management
Six Sigma

  About us  
  Services  
  Business Insights  
  Nieuws  
  Events  
  Carrière